✅ Selmo PTF – Process flow checklist & milestone overview

Goal

This checklist describes the process, the checks and approvals within the PTF process. It serves as guidance for the project team and as a basis for project controlling, scheduling, and quality assurance.

Each phase of the PTF ends with a defined milestone, the fulfillment of which is checked and documented.


1. Process flow – step-by-step checklist

No.
Process step
Goal
Result / deliverable
Responsible
Acceptance criterion

1

PTF start / scope definition

Clarify project boundaries, objectives, standards, and roles

PTF-SCOPE document, supplier list

Project management / PTF lead

- All suppliers named - Project scope approved

2

Process capture (P)

Understand the physical flow and logic

PTF-PROC, PTF-PARAM

Process owner

- Flowchart complete - Parameters defined

3

Technology analysis (T)

Define technologies, devices, interfaces

PTF-TECH, PTF-IO, PTF-IF

Mechanics / Electrical / IT

- Technology matrix complete - Signals assigned

4

Function definition (F)

Describe functional logic, monitoring, test cases

PTF-FUNC, PTF-SAFE

Automation / Software

- Function sheets created - Safety logic documented

5

Data integration & review

Check completeness and Selmo compliance

PTF review protocol

PTF lead / Quality

- All artifacts submitted - no open items

6

Risk assessment & deviations

Document and assess non-conformities

PTF-RISK

Quality / Safety

- Risks assessed - Measures assigned

7

PTF review meeting

Technical and organizational approval

PTF review report

Project management / PTF lead

- All disciplines present - Decisions documented

8

PTF approval (release)

Official authorization for modeling

PTF-RELEASE document

Project management / customer

- Signatures present - Version archived

9

Transfer to Selmo modeling

Import PTF data into Selmo Studio

PTF-XML / model export

Automation / Software

- Import successful - Structure mappable

10

Project closure / audit trail

Retrospective, lessons learned, archiving

PTF final / lessons learned report

PTF lead / Quality

- Documentation complete - Audit trail secured


Additional check for each phase

Before completing each phase, it must be checked that:


2. Milestone overview (PTF lifecycle)

Milestone
Time
Result / approval
Responsible
Decision criterion

M1 – project start

Week 0

PTF scope, supplier list, objective definition

Project management

Project objective and boundaries approved

M2 – process definition completed

Week 2–3

PTF-PROC, PTF-PARAM

Process owner

Process complete and reviewed

M3 – technology analysis completed

Week 4–5

PTF-TECH, PTF-IO, PTF-IF

Mechanics / Electrical / IT

Interfaces, signal structure aligned

M4 – function definition completed

Week 6–7

PTF-FUNC, PTF-SAFE

Automation / Software

Functional logic consistent, safety assessed

M5 – PTF review meeting

Week 8

PTF review protocol, PTF-RISK

PTF lead / Quality

All artifacts complete, risks assessed

M6 – PTF release

Week 9

PTF-RELEASE

Project management / customer

Official approval for Selmo modeling

M7 – Selmo model imported

Week 10

Selmo model (Plant → HWZ → SEQ → Zones)

Software / automation

Import successful, code generatable

M8 – SoftFAT (digital twin)

Week 11–12

Simulation / emulation successfully tested

Automation / Quality

Communication and sequences validated

M9 – project closure (PTF final)

Project end

Lessons learned, audit trail, archiving

PTF lead / Quality

Documentation complete, audit passed


PTF process flow (simplified)


Quality assurance per milestone

Each milestone is only reached when:

  • The preceding steps are fully completed are

  • The Check and review documents have been approved

  • The PTF lead a formal confirmation for handover has been given

  • The Project management the result is approved in writing


Recommendation for project practice

  • Plan each PTF phase as a standalone work package with deliverables and review.

  • Use the milestones M1–M9 as mandatory points in the project schedule.

  • Conduct review meetings in an interdisciplinary manner (mechanics, electrical, software, quality, management).

  • Store all approved artifacts in a versioned PTF repository there.

  • Link PTF milestones with the project milestones in your PM tool (MS Project, Jira, Notion etc.).


Conclusion

This checklist and milestone overview ensure:

  • clear structure and responsibilities,

  • traceable progress,

  • plannable reviews,

  • and verifiable approvals.

This makes the PTF process a measurable part of project management – and the result a fully documented, standards-compliant, and deterministic system according to the Selmo standard.

Last updated

Was this helpful?